New Jersey School Boards Association

Annual Bond Referenda Survey

Overview: 2000, 1999, 1998,1997

 

 

2000

1999

1998

1997

# of Elections

89

89

75

74

# of Proposals Approved

68.66*

63.5*

45

39

% of Proposals Approved

77.2%

71.3%

60%

52.7%

Total Spending Proposed

$1.298
billion

$1.199 billion

$893.919 million

$867.91 million

Total Spending Approved

$1.043
billion

$779.867 million

$487.215 million

$473.91 million

% Spending Approved

80.4%

65%

54.5%

54.6%

Voter Turnout

24.09%

24.76%

26.64%

28%

(based on 30 of 74 elections)

* Fractions indicate split results in districts where referenda included more than one question.

† 71.4% of bond referenda on the ballot prior to the July 18, 2000 signing of the Educational Facilities Construction and Financing Act were approved by voters. 80.9% of the proposals on the ballot after July 18 were approved.